A flagship project is sponsored by the CEO and has a critical go-live date. The project’s product requires a regulatory review and approval before it can go live. The CEO instructed to allow only 2 weeks for regulatory approval in the schedule; however, the director for the regulatory liaison indicated 6 weeks was a more realistic timeline.
What should the project manager do?

الخيارات

  • A Meet with the CEO and the director to discuss and register it as a major risk if agreement cannot be made.
  • B Proceed with the direction given by the director for the regulatory liaison, as they are the subject matter expert (SME).
  • C Schedule final testing activities in parallel with the regulatory approval activities to compensate for lost time.
  • D Follow the CEO's directive, as they are the highest authority in the company and are the ultimate decision maker.