A project management office (PMO) is currently stretched for project control resources. Specifically, the cost control resources are short of the staff required for this activity level. A new project is about to start soon.
What should the project lead do to obtain the needed resources?

الخيارات

  • A Prepare to perform the duties of the cost controller for the duration of the project.
  • B Meet with the PMO team and review the resource management plan ahead of the project kickoff to ensure resource availability.
  • C Inform the project sponsor and initiate a recruitment exercise outside of the PMO.
  • D Evaluate running the project without the required resources and depend on the lessons learned from similar past projects.