A team has noticed a labeling mistake in two different prototypes. The mistake resulted in a need to apply a different destructive testing plan for each prototype. This resulted in a decline in team morale.
What should the project lead do?

الخيارات

  • A Bring in subject matter experts (SMEs) to coach the team.
  • B Lead the team through the next sprint to prevent a similar issue.
  • C Influence stakeholders to support the team allowing recovery within limits.
  • D Use cost and time contingencies to mitigate a project baseline impact.