A project manager has taken over a project and realizes a number of the suppliers responsible for the delivery have not done an implementation as complex and large as this project. The project manager reviews the risk log and logs this as a risk. Three months later, two suppliers have missed key milestone dates and delivered substandard work.
What should the project manager do?

الخيارات

  • A Execute the risk response plan and update the action register.
  • B Support the suppliers by providing them with additional resources.
  • C Execute the risk response plan and update the issue log.
  • D Ask suppliers to submit a revised plan and schedule.