A railroad construction project is in the planning stage. During a monthly progress meeting, an external project manager from the sponsoring organization mentioned there is a potential delay in the design completion date. The external project manager wants to know the impact of this delay on the overall project completion date in the next monthly meeting.
Which three actions should the internal project manager take next? (Choose 3)

الخيارات

  • A Validate the critical path method (CPM).
  • B Perform variance analysis.
  • C Establish what-if scenario analysis.
  • D Execute a Monte Carlo simulation.
  • E Determine the schedule performance index (SPI).