A project's planning process is finished, and all resources were budgeted for and approved by senior management. Just before the kickoff meeting, a member of the production department realizes that the plan does not meet the requirements for their area.
What should the project manager have done during the planning process?

الخيارات

  • A Developed a good resource estimation in the planning process
  • B Included all functional managers in the planning process
  • C Monitored the budget variations during the planning process
  • D Distributed the resource estimates to all areas during the planning process