After establishing a cost baseline and the appropriate cost management plan for a complex hybrid project, the project is still being challenged with cases of budgetary variations. What should the project manager do?

الخيارات

  • A Approve budget variations upon request only when the cost performance index (CPI) is above 1.
  • B Track budget variations and work with the key stakeholders to adjust as necessary.
  • C Reject budget variations upon request to discourage the waste of money on the project.
  • D Approve budget variations upon request to encourage rapid delivery of some components.