An agile project team has not been delivering as expected. During a team review, it was revealed that the product backlog is in poor condition.
With support from the project management office (PMO), what should the project manager do?

الخيارات

  • A Train the product owner to create better backlog items.
  • B Ask the team to create and update backlog items.
  • C Train the team on how to create and maintain backlog items.
  • D Ask an experienced team member to maintain the backlog.