A project manager has been assigned to lead a complex software development project. The project manager wants a team that is both experienced and cohesive.
What should the project manager do to build the team?

الخيارات

  • A Ensure the team has a good mix of team members with varying levels of seniority.
  • B Assign to the project only team members who have worked together in similar projects.
  • C Review human resources (HR) competence and personality reports to determine the best-fit candidates.
  • D Prepare detailed project documentation and ensure the team members are aligned.