A project lead is managing an agile project. The project activities, which have been placed in a backlog, still need to be refined and prioritized.
What should the project lead use for backlog refinement considering the sprints are 2 weeks long?

الخيارات

  • A Ninety minutes every three sprints going through stories that are higher priority.
  • B Sixty minutes every sprint going through stories with higher story points.
  • C Sixty minutes every sprint going through stories that are higher priority.
  • D Ninety minutes every three sprints going through stories with higher story points.