A project sponsor is replaced during a hybrid project closure. The new project sponsor wants to change all of the project documentation to reflect a fully predictive approach.
What should the project manager do next?

الخيارات

  • A Ask the team to estimate the time it will take to update the documentation.
  • B Set up a meeting with the new project sponsor to understand their concerns.
  • C Review the key existing project documents with the new project sponsor.
  • D Address the issue during the lessons learned session of the closing phase.