Presented with flowcharts of the organization's operations, stakeholders are unfamiliar with several recorded processes, and others note that some recorded processes were discontinued. The project sponsor notices that the chart is several years old and wants an updated version immediately.
What should the project manager do?

الخيارات

  • A Raise a change request and ask the project sponsor to approve it so the flowcharts can be updated.
  • B Assemble and create teams of experts and stakeholders to update flowcharts to reflect current conditions.
  • C Assemble the entire project team to produce new flowcharts from current versions.
  • D Work with a consultant and the project sponsor to produce new flowcharts.