During project execution, a project manager is leading the team to work on the project schedule. During a meeting, the team has difficulty understanding the complexity of a task and is unable to provide an estimate for the required resources.
What should the project manager do first to resolve this issue?

الخيارات

  • A Report to the sponsor that there is a new challenge in the project.
  • B Refer to the organization's lessons learned from past projects.
  • C Engage an external expert to provide the estimation.
  • D Register the issue as a risk in the risk register.