Due to an anticipated expansion, a company procured new technology. The project team responsible for using this technology does not have experience with it.
What should the project manager do?

الخيارات

  • A Hire project resources with experience using the new technology.
  • B Assess the benefit of using new technology versus old technology.
  • C Propose training for the project team in batches on the new technology.
  • D Request incentives for the team to use the new technology.