اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 464 من 874

كل الأسئلة

Customers are concerned about the quality of an interim software system for a project. The quality control team has approved the software, but the customers are complaining that some functions do not comply with the requirements.
What should the project manager do to prevent this from happening again?

الخيارات

  • A Review the risk impact of quality nonconformance.
  • B Revise the product acceptance specifications.
  • C Revise the quality management plan.
  • D Review the communications management plan.

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.