A project manager is leading the development and delivery of a strategic product that must be delivered on time. The project is facing technical issues that could significantly impact the budget and ability to deliver some of the product features.
What should the project manager do first to resolve the issue?

الخيارات

  • A Assess the impact of the feature on the project and ask for a contingency.
  • B Record the situation in the risk register and communicate it to stakeholders.
  • C Schedule a meeting with the team and management to discuss options.
  • D Develop a quality management plan to clearly identify how features should be classified.