اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 461 من 874

كل الأسئلة

A project has progressed significantly and is getting close to completion. The project manager observed that team members are no longer focused and have started arriving to work late.
What should the project manager do?

الخيارات

  • A Engage functional managers to secure roles for team members.
  • B Ask for replacement project team members.
  • C Penalize team members who arrive to work late.
  • D Hold motivation sessions to keep team member morale high.

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.