اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 457 من 874

كل الأسئلة

Project stakeholders have provided a team with requirements that will take at least one year to complete. The project sponsor advised that they need to see some return on investment (ROI) soon.
What should the project manager do?

الخيارات

  • A Request additional funding from the project sponsor to accelerate delivery.
  • B Discuss reducing the requirements with the project sponsor in order to release the product earlier.
  • C Prioritize the work into incremental features that can be delivered iteratively.
  • D Acknowledge that the benefits cannot be realized any sooner due to the nature of the requirements.