The project sponsor wants to obtain quick feedback from end users for a product under development. The roadmap is extensive and will not be completed for quite some time.
What should the project manager do?

الخيارات

  • A Advise the stakeholders that they will need to wait until development is completed in order to get actual end-user feedback.
  • B Hire additional resources to accelerate the schedule and deliver the product faster in order to get actual end-user feedback.
  • C Work with the stakeholders to determine the minimum requirements needed to get valuable end-user feedback and revise the project schedule.
  • D Advise the stakeholders to share images of the finished product in order to obtain valuable feedback from end users.