During project planning activities, a project manager identifies potential delays in obtaining resources required for a project. This will significantly impact the construction time line.
What should the project manager do?

الخيارات

  • A Create a change request to increase the cost of resources.
  • B Delay the project until additional resources can be identified.
  • C Review and update the project management plan to accommodate the delays.
  • D Speak with the project sponsors about changing the project management plan.