A project manager is working on a project to implement a set of business processes that involves several organizations. During the project, the project manager observes frequent misunderstandings among stakeholders.
What should the project manager do first to manage the stakeholders' needs?

الخيارات

  • A Develop a joint stakeholder quality policy for the project and seek a commitment from all organizations.
  • B Ask the project team to follow the organization management layers when communicating with the stakeholders.
  • C Ensure that the communications management plan built on each stakeholder's expectations is up-to-date.
  • D Conduct individual interviews with key stakeholders to understand all concerns.