An organization is undergoing an agile transformation and migrating most of its projects from a predictive approach. The CFO expressed a concern that predictability on both costs and scope will be lost with the new agile approach.
What should the project manager do?

الخيارات

  • A Provide mentoring to the CFO, who is a key stakeholder in the project, and clarify the benefits of an agile approach.
  • B Submit a report to all key stakeholders on the cost-benefit analysis of the new approach and detail how the company will save money.
  • C Apply influence with other key stakeholders on the board to mitigate any risks that may be generated by the CFO's position on the matter.
  • D Ask the CEO to intervene by asking for support from the executive board to accelerate the company’s transformation.