A project team that has been working at the client site will soon be allocated to another project. The deployed solution is working perfectly, and the end users are well trained and operating smoothly on the system.
What should the project manager do to ensure proper project transition to the end users?

الخيارات

  • A Make sure that all manuals and guides are updated and ready before handing them over to the end users.
  • B Confirm that the deliverables list is complete, there are no missing items, and all are delivered and functioning properly.
  • C Schedule a formal handover meeting with the system administrators and end users based on a predefined project checklist.
  • D Conduct a final round of training and system troubleshooting to ensure that the end users are aware of all project information.