A project is starting its first iteration out of eight. The team realizes that a key deliverable will depend on the acquisition of a new device.
What should the project manager do?

الخيارات

  • A Register a risk and monitor its exposure variation.
  • B Assign a resource from the core team to handle the acquisition.
  • C Update the status report with information about this dependency.
  • D Register a risk and escalate it to the project sponsor.