اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 381 من 874

كل الأسئلة

A project manager with agile experience is part of an organization that is transitioning to agile. The project manager was assigned to the first agile project by the project management office (PMO). The PMO manager asked the project manager if an existing governance from a previous project would be suitable to use in the current agile project.
How should the project manager respond?

الخيارات

  • A This framework is not appropriate for agile.
  • B An agile approach is different.
  • C An agile approach is easily adaptable.
  • D This is a learning experience for the agile team.

النقاشات