A project manager is assigned to a research project. The project team has been selected and has worked together on other projects. Based on the project documentation, team members seem to be working at their own pace and have had little interaction with the project manager.
What should the project manager do to have a high-performing team?

الخيارات

  • A Invite team members to an informal meeting to get to know one another.
  • B Encourage the team to define the ground rules for performance.
  • C Set up regular project status meetings and invite all team members.
  • D Set up individual calls to follow up on each team member's progress.