A high-tech borehole project was initiated with the goal of providing water for a rural community of 1500 villagers located in an arid region. The project was completed with a cost performance index (CPI) of 1.09 and a schedule performance index (SPI) of 0.93. Six months after its completion, it is determined that the villagers could not access water.
What caused this situation to occur?

الخيارات

  • A The project was delivered above budget.
  • B The requirements gathering was inadequate.
  • C The project was completed behind schedule.
  • D The risk analysis was inadequate.