اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 363 من 874

كل الأسئلة

A project manager has been assigned to a new project. The project sponsor has requested a detailed time line, but the project includes some deliverables that are not yet clearly defined.
Which project management approach should the project manager advise using?

الخيارات

  • A As the project sponsor has requested a detailed time line up front, an agile approach is the best option.
  • B As the project includes elements that are not yet clearly defined, an agile approach is the best option.
  • C As the project appears to have both agile and predictive elements, a hybrid approach is the best option.
  • D As the project includes elements that are not yet clearly defined, a predictive approach is the best option.

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.