A team is using an agile approach to maintain the project backlog. A new project obstacle was identified as a blocker and added to the backlog list. The team is facing challenges to remove this obstacle.
What should the project manager do next?

الخيارات

  • A Make changes to reprioritize the backlog because of the obstacle.
  • B Reject the obstacle and present the partial solution to the customer.
  • C Focus on generating business value despite the obstacle.
  • D Escalate the obstacle to a servant leader for resolution.