A project manager is in the process of authoring the communications management plan for a new project. One of the project’s stakeholders has a habit of posting work updates on social media, which may include confidential project status updates.
What should the project manager do?

الخيارات

  • A Ensure that sensitive information is not included in stakeholder updates.
  • B Review social media access and restrict it to ensure confidentiality.
  • C Review the protocols and security measures to ensure confidentiality.
  • D Ensure that social media posts related to the project are removed.