اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 352 من 874

كل الأسئلة

A project team has experienced deliverable delays in the last few iterations. During the retrospective, the team realizes that the quality issues identified are because the quality process is outdated.
Who should the project manager ask to update the process?

الخيارات

  • A Quality lead
  • B Project team
  • C Project management office (PMO)
  • D Product owner

النقاشات