A technical subject matter expert (SME) identifies an occurrence that should be captured in the project’s lessons learned. The SME asks the project manager to write, document, and include it in the lessons learned register.
What should the project manager do?

الخيارات

  • A Ask the SME to document and capture the occurrence.
  • B Assign the documenting task to a project team member.
  • C Request the SME to wait until the project closure phase.
  • D Take ownership of documenting this information.