اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 344 من 874

كل الأسئلة

At the end of a meeting, a functional manager takes the project manager aside to raise some concerns on behalf of a project team member who is unclear about their role and responsibilities for the project. What should the project manager do in this situation?

الخيارات

  • A Develop a work plan for the project team member with the help of the resource manager.
  • B Ask the functional manager to create a specific responsible, accountable, consult, and inform (RACI) chart for the team member.
  • C Advise the functional manager and the project team member to review the resource management plan.
  • D Tell the functional manager and the project team member to review the project charter.

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.