The project is delayed due to the high amount of major changes requested by different stakeholders at different stages of the project. If the project continues on the same path, it will consume twice the time and budget planned.
What two actions should the project manager take to be more cost-effective? (Choose 2)

الخيارات

  • A Update the project management plan with the new timeline.
  • B Reinforce team communication.
  • C Leverage work between team members.
  • D Conduct a stakeholder analysis.
  • E Adopt an incremental approach.
  • F Update the project management plan with the new timeline.
  • G Reinforce team communication.
  • H Leverage work between team members.
  • I Conduct a stakeholder analysis.
  • J Adopt an incremental approach.