اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 328 من 874

كل الأسئلة

During a retrospective review, many project team members say they are not completing tasks during the iterations because of interruptions and requests for help from other teams. As a team facilitator, what should the project manager do to avoid this?

الخيارات

  • A Recommend to the project team members that they should improve their planning and make their stories smaller.
  • B Reunite with the project team members affected and tell them not to reduce the team's capacity.
  • C Hire a coach to help all project teams to improve their abilities to solve problems on their own.
  • D Identify the problem's root causes and define the ground rules with all project team members to minimize interferences.

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.