During the course of a project, the project manager's immediate director is communicating directly with the client to approve changes without the project manager's knowledge. This is causing confusion in the project team where the scope is changing in the background, but only being mentioned in project meetings.
What should the project manager do?

الخيارات

  • A Discuss the issues with the project team and let them know that the project manager will handle scope changes.
  • B Communicate directly with the director and inform them of the communications management plan.
  • C Communicate directly with the client stating that any scope changes must go through the project manager.
  • D Review the stakeholder engagement plan and put in place any existing actions accordingly.