اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 322 من 874

كل الأسئلة

A new resource has joined an iterative project team. The project manager notices that the resource is unable to complete the deliverables on time.
How should the project manager address this situation?

الخيارات

  • A Address the lack of performance by coaching the new team member.
  • B Provide performance feedback as part of the retrospective ceremony.
  • C Request a more efficient replacement resource from the project sponsor.
  • D Discuss options to improve performance with the resource manager.

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.