اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 302 من 874

كل الأسئلة

A key project stakeholder who was a big supporter and motivator for the project team is leaving the organization. The project team is experiencing low morale and poor teamwork.
What should the project manager do to improve morale?

الخيارات

  • A Set goals and push the team to achieve the goals.
  • B Build team connections and emotional bonds
  • C Forge consensus through team participation.
  • D Identify the wants and aspirations of the team.