اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 296 من 874

كل الأسئلة

A project team with members from many different countries is struggling to cooperate. The project manager accepted these difficulties during the storming phase of team development, but the team has not moved to the next phase. The project is beginning to fall behind schedule.
What should the project manager do to move the team to the norming phase?

الخيارات

  • A Speak with the project sponsor about changing the team composition.
  • B Plan social activities to help foster stronger interpersonal relationships and identify shared goals.
  • C Show the team the schedule impact of their communication issues and encourage them to put their differences aside.
  • D Find out who is behind the issues and apply progressive disciplinary techniques.