The product team is progressing with a prototyping approach to deliver a multiyear business initiative. A few user stories are taking longer to be delivered.
What should the project manager do?

الخيارات

  • A Discover the gaps in the communications management plan and address them accordingly.
  • B Inform stakeholders about the delay during project updates.
  • C Determine the risks and identify a resolution during the retrospective meeting.
  • D Determine cross-dependencies and plan a spike in the next sprint.