The project manager just started leading a project team from which the previous project manager resigned. After a quick evaluation of the project, it is apparent that team morale is low due to continuous disagreement about how to complete tasks. Tasks are taking longer than forecasted and the project is off schedule.
What should the project manager do?

الخيارات

  • A Crash the project timeline to ensure the project is back on schedule.
  • B Issue a change request to extend the project schedule based on identified delays.
  • C Conduct a meeting with the project team to discuss and address the sources of disagreement.
  • D Inform the stakeholders that the project will be delayed due to previous team management.