The project team follows a hybrid framework for its delivery. During the execution of a project, the team learns of a new compliance requirement that has to be delivered before any other requirements.
How should the project manager address this situation?

الخيارات

  • A Include the compliance lead in the stakeholders list and wait for the next status meeting.
  • B Ask the team to include the compliance requirement in the current sprint and deliver it.
  • C Collaborate with the compliance team member to review and prioritize the requirement's delivery.
  • D Add the new compliance requirement to the backlog as the technical team does not have any capacity.