اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 254 من 874

كل الأسئلة

During a daily standup meeting, a roadblock was raised that is preventing one of the team members from proceeding with work. The project manager figures out that it is due to a technical issue.
What should the project manager do to prioritize this critical impediment?

الخيارات

  • A Solve the issue for the team member.
  • B Coach the team to come up with their own solution and add it to the next sprint.
  • C Perform a brainstorming session to address the issue and add the solution to the sprint.
  • D Escalate the issue to the software vendor for technical resolution.

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.