اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 244 من 874

كل الأسئلة

A company has a lot of experience with predictive projects. The project management office (PMO) has been trying to implement iterative tools within the project management framework, and the project manager has been asked to use these tools in their current project. After the successful implementation of the iterative tools, the PMO asks the project manager to determine the benefits these tools brought to the project.
What should the project manager do?

الخيارات

  • A Update the communications management plan to consider performance review meetings with the project stakeholders.
  • B Determine the data to be monitored during the project as well as the expected performance and targets.
  • C Conduct reviews with stakeholders to discuss the potential benefits the approach may have to the project.
  • D Prepare and submit a status report to the steering committee to update performance monitoring.

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.