اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 242 من 874

كل الأسئلة

A company's project management office (PMO) has started to implement iterative tools. A project manager is starting a new project and has identified an opportunity to use the iterative tools. One of the senior managers is concerned about this modified framework as it is fairly new to the company.
What should the project manager do first?

الخيارات

  • A Send documentation to the senior manager about the advantages of the new framework.
  • B Organize individual sessions with the stakeholders to build awareness and trust in the new framework.
  • C Look for external training on the new framework to eliminate the risk of low engagement from stakeholders.
  • D Escalate the senior manager's concern to the project sponsor and distribute the status to the team.

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.