A project manager presented the project schedule to the main stakeholders. They have requested that the project be completed two months earlier than the scheduled date.
What should the project manager do?

الخيارات

  • A Hold a stakeholder meeting to align timelines and scope expectations.
  • B Reduce the scope of the project by removing activities and shortening the timeline.
  • C Crash the schedule to shorten the timeline while keeping the scope unchanged.
  • D Update the cost management plan to allocate more resources to the project to finish the scope earlier.