A company was awarded a project in a dangerous location that poses several high-level risks for employees. Help is needed to train the employees on major safety and health factors. The project is ongoing and uses a hybrid approach. The project will be conducted in multiple sites, with several development iterations running in parallel.
How should the project manager handle this situation?

الخيارات

  • A Negotiate a contract and form a partnership with a local authority for medical and security support services.
  • B Allocate and use part of the project's contingency reserves for training purposes.
  • C Hire only local resources who are aware of the territory's hazards, providing employment to the local community.
  • D Perform a retrospective and update the risk register and resource management plan regarding the necessary budget for training.