السؤال 233 من 874

كل الأسئلة

In a software development project, the product owner and development team agree on a sprint backlog. The highest priority in the backlog is to build a payment module. The team worked on the module during the first half of the sprint, but now two developers want to spend the rest of the sprint focusing on refactoring another feature that might create issues in the future.
What should the project manager do?

الخيارات

  • A Restate to the developers the importance of focusing and meeting the sprint goal.
  • B Praise the developers for their proactivity and focus on quality.
  • C Let the developers focus on the refactoring work and discuss it in the retrospective.
  • D Escalate the issue to the developers' functional managers.