Two weeks after the approval of the project management plan for a global project, the project manager noticed that it was approved based on a different level of understanding by international stakeholders and is not what the project manager presented for approval. What should the project manager have done to prevent this from happening?

الخيارات

  • A Reviewed all the approvals immediately after the kick-off meeting was over.
  • B Ran separate kick-off meetings for each culture and time zone.
  • C Validated each stakeholder's understanding during the kick-off meeting.
  • D Sent the meeting minutes to the stakeholders after the kick-off meeting.