One of the main inputs required for a deliverable is missing due to a miscommunication between the vendor and project manager. Because of the missed deliverable, the critical path of the project is extended.
What should the project manager do next?

الخيارات

  • A Start an audit of the vendor's processes and procedures.
  • B Make a detailed analysis on vendor issues during the project.
  • C Execute a contingency plan to address the issue with the vendor.
  • D Review lessons learned from previous projects with this vendor.